Industrial demolition, dismantling and site remediation projects

CSR Gyprock (Board Line Removal)

Demolition, asbestos removal in a live plant 

As a result of the installation and commissioning of a new Gyprock mill and board line, the redundant board line and sections of the existing factory had become redundant and were scheduled for demolition. The new facility had been built adjacent to and over the existing line and factory.

IDS were required to integrate and coordinate the demolition and removal of the redundant production equipment with the new production process, ongoing construction activities and the progressive removal of asbestos containing materials. The line removal was completed ahead of schedule with the building demolition being completed during the Christmas holiday shut down period. No production delays were experienced due to demolition activities.